Page 32 - TSAB Adult B FINAL (1)
P. 32

This document was classified as: OFFICIAL



            Hospitals NHS Foundation Trust,
            GP
            Housing Group 1
            Housing Group 2
            Mental Health NHS Foundation Trust
            Area B Borough Council Adult Social Care
            Area A Borough Council Adult Social Care
            Ambulance Service
            Police
            Substance Misuse Services
            Council Housing Department Area A


              Historical summary reports will be requested from:

            Area B Children’s Social Care
            Area A Children’s Social Care

          9.  Family Involvement


              A key part of undertaking a SAR is to gather the views of the family and share findings with them prior
              to finalisation of the report. Josh was estranged from his family. At the time of the writing of these
              terms of reference, TSAB were making attempts to make contact with family members. The
              Independent Reviewer will make arrangements to meet with the family.


          10. Project Plan dates:

                                                                                        Date
                        Scoping Meeting (Governance Group)                              19/03/2019

                        Terms of Reference updated                                 A  As above
                        Agency Authors’ Briefing                                        As above
                        Agency Review Reports submitted                                        30/04/2019
                        Review of Reports by Independent Author                         1-3/05/2019
                        Distribution of Reports to all Learning & Reflection Workshop   08/05/2019
                        attendees
                        Learning and Reflection Workshop (Full Day)                     16/05/2019
                        First Draft Overview Report to all attendees                    21/06/2019
                        Learning and Reflection Review Workshop                         03/07/2019

                        V2 Overview report circulated to workshop attendees             17/07/2019
                        Comments on V2                                                  24/07/2019
                        V3 to SAR/Governance Sub Group                                  23/08/2019
                        SAR / Governance Sub-Group to agree workable achievable         25/09/2019
                        recommendations and agree report prior to presentation at
                        Board.
                        Presentation to TSAB Meeting                                    28/11/2019